Which of the following statements is true about critical paths in networks?
There may be multiple critical paths with the same duration through a network.
The average duration of all paths on the network is equal to the duration of the critical path.
Activities on the critical path may have a non-zero float time.
There is only one critical path in every network.
The critical path is the shortest path in the network.
Given the following network:
Given the following network:
Given the following network and activity table: