9.08 Planning activities with dependencies

Worksheet
Project networks
1

Consider the following network:

a

Which activities are dependencies for activity C?

b

What are the initial activities?

c

What are the final activities?

d

Which activities have no dependencies?

2

Consider the following network:

a

Which activities are dependencies for activity D?

b

What are the initial activities?

c

What is the final activity?

d

Which activities have no dependencies?

3

Consider the following network:

a

Which activities are dependencies for activity G?

b

What are the initial activities?

c

What is the final activity?

d

Which activities have no dependencies?

4

Consider the following network:

a

Which activities are dependencies for activity E?

b

What is the initial activity?

c

What is the final activity?

d

Which activity has no dependencies?

5

Consider the following network:

a

Which activity is a dependency for activity F?

b

What is the initial activity?

c

What is the final activity?

d

Which activity has no dependencies?

6

Consider the following network:

a

Which activities are dependencies for activity F?

b

What is the initial activity?

c

What is the final activity?

d

Which activity has no dependencies?

7

Consider the following network:

a

Which activity is a dependency for activity E?

b

What are the initial activities?

c

What are the final activities?

d

Which activities have no dependencies?

8

Consider the following network:

a

Which activities are dependencies for activity E?

b

What are the initial activities?

c

What are the final activities?

d

Which activities have no dependencies?

9

For each of the following networks, complete an activity table by listing the duration and direct dependencies for each activity. If an activity has no dependencies, write an X.

a
b
c
d
e
f
10

Construct a project network for each of the following activity charts:

a
ActivityDurationDependencies
A1-
B8A
C1A
D3B,C
E9D
b
ActivityDurationDependencies
A7-
B4-
C5-
D5A,B,C
E4D
F7D
c
ActivityDurationDependencies
A1-
B4-
C3A
D7B
E3-
F5C,D
G5F,E
d
ActivityDurationDependencies
A7-
B2-
C3A,B
D7A,B
E1C
F9D
e
ActivityDurationDependencies
A2-
B7-
C3-
D8A,B,C
E4D
F5D
G7E,F
f
ActivityDurationDependencies
A2-
B9A
C4A
D3B,C
E4D
g
ActivityDurationDependencies
A9-
B8-
C3A
D7B
E2-
F4C,D
G8F,E
h
ActivityDurationDependencies
A2-
B8-
C7-
D7A,B,C
E7D
F2D
G8E,F
Sign up to access Worksheet
Get full access to our content with a Mathspace account