9.05 Schedule problems and critical paths

Interactive practice questions

Which of the following graphs represent the activity chart given?

Activity Duration Dependencies
$A$A $1$1 -
$B$B $8$8 $A$A
$C$C $1$1 $A$A
$D$D $3$3 $B,C$B,C
$E$E $9$9 $D$D

A

B

C

D
Easy
1min

Which of the following graphs represent the activity chart given?

Easy
< 1min

Which of the following graphs represent the activity chart given?

Easy
1min

Which of the following graphs represent the activity chart given?

Easy
< 1min